Repair Project Phase 1, 2015

Stuart Billington

Phase 1 of the Repair Project was carried out between January and July 2015.
The architect for the project was Andy Burrell of Carden & Godfrey.
The main contractor was Richard Soan Roofing Services of Lewes.
The total cost was £244,000, and this was financed as follows:

English Heritage/Heritage Lottery Fund grant£118,000
Chichester Diocese grant£  72,000
Listed Places of Worship Scheme (VAT refund)£  36,000
Garfield Weston Foundation grant£  10,000
St John sub Castro fundraising£    8,000

Phase 1 was made up of the following elements:
New slate roof to the Nave
New flat roof to the Tower
New tiled roof to the Sanctuary
New tiled roof to the Clergy vestry
Repairs to the Chancel roof
Repairs to the Organ vestry roof
Repairs to buttress cappings and wall copings
Repairs to brickwork and flintwork
Weathervane restoration

Click the links to see more details of the work carried out.

This page was added on 18/11/2017.

No Comments

Start the ball rolling by posting a comment on this page!

Add a comment about this page

Your email address will not be published.